NGCP completes key parts of Mindanao-Visayas power link

BW FILE PHOTO

NATIONAL Grid Corp. of the Philippines (NGCP) said on Thursday that it is “significantly closer” to interconnecting the electricity grids in Mindanao and the Visayas after it completed key components of the project, including facilities in areas where they will link.

In a statement, the privately owned power transmission company said it is done with the construction of the cable terminal stations in Santander, Cebu and Dapitan, Zamboanga del Norte, as well as the installation of two 92-kilometer 350-kilovolt (kV) high voltage direct current (HVDC) power cables and two 92-kilometer fiber optic cables.

NGCP said these “critical” components of the P52-billion Mindanao-Visayas interconnection project “are now complete and ready for energization.” The Mindanao grid will be linked to the Visayas grid via an HVDC system, which has a 450-megawatt initial capacity.

“We hoped this would finish on time, but factors beyond our control required an adjustment to our project timeline. We are working double-time to complete the overhead transmission line portions and advance the project to its commissioning stage to connect the Luzon, Visayas, and Mindanao grids,” the company said.

It said site acceptance tests were conducted at the Dapitan and Santander cable terminal stations to make sure the installed facilities meet NGCP’s requirements.

The company targets to complete the project by the end of the year.

“NGCP continues to appeal for the support of the local and national government to push this into fruition. Delays in local government permitting, and right-of-way issues from slow judicial processes and unsupportive landowners continue to delay our efforts,” it added.

NGCP said the target completion date remains the same even after encountering delays because of the pandemic. The delays were caused by restrictions on the entry of foreign experts, work suspension, and manpower reduction.

The submarine cable component of the project was originally scheduled for June 2021 after work started in November 2018. But the first submarine cable was damaged by a third-party vessel and repair was completed only in November 2021.

Another completed component is the energized Lala-Aurora 138-kV transmission line, which was finished on Feb. 19, 2022, to improve the reliability of power transmission services between Lanao del Norte and provinces in the Zamboanga Peninsula.

Up for completion are other components such as the Dumanjug bus-in to Colon-Samboan 138-kV transmission line, for December 2022; the Dapitan-Lala 350-kV transmission line, Kauswagan-Lala 230-kV transmission line, and Kolambugan-Lala 20-kV transmission line, for August 2022; and the Dumanjug-Santander 350-kV transmission line, Magdugo-Dumanjug 230-kV transmission line, and Dumanjug-Alegria 20-kV transmission line for October 2022.

NGCP holds a 25-year concession and a 50-year franchise to expand and operate the country’s power transmission grid. It operates the country’s transmission network linking power generators and distribution utilities.

Publicly listed Synergy Grid & Development Phils., Inc. indirectly controls 60% of the outstanding capital stock of NGCP, its sole operating asset, with an effective equity interest of 40.2% consisting of common shares.

On Thursday, shares in Synergy Grid slipped by 0.33% or four centavos to close at P12.16 each. — Victor V. Saulon

Your information is secure and your privacy is protected. By opting in you agree to receive emails from us. Remember that you can opt-out any time, we hate spam too!

Latest

News

PHILIPPINE STAR/ MICHAEL VARCAS WASHINGTON D.C. — The United States is seeking to form a coalition of countries to drive negotiations on a global...

News

Buildings are seen along EDSA in Quezon City. — PHILIPPINE STAR/ MIGUEL DE GUZMAN By Diego Gabriel C. Robles  THE WORLD BANK (WB) upgraded...

News

Heavy traffic is seen on the southbound lane of EDSA in Cubao, Quezon City. — PHILIPPINE STAR/ MIGUEL DE GUZMAN THE PHILIPPINE auto industry’s...

News

REUTERS THE BANGKO SENTRAL ng Pilipinas (BSP) may deliver a second off-cycle rate hike in early November when the US Federal Reserve is expected...

News

Vendors arrange their goods at a public market in Manila. — PHILIPPINE STAR/ RUSSEL A. PALMA THE ASIAN Development Bank (ADB) is planning to...

Editor’s Pick

With the reversal of the 1.25% rise in National Insurance Contributions happening on the 6th of November, employers across the nation have an opportunity...

You May Also Like

News

BW FILE PHOTO GROSS BORROWINGS by the National Government reached P2.6 trillion as of end-September as it continued to raise funds to respond to...

News

KARASOLAR.COM TENA, Ecuador — Ecuador’s rainforest Achuar people say their ancestors long dreamed of a “fire canoe” or “electric fish” that would let them...

News

REUTERS By Luz Wendy T. Noble, Reporter The country’s foreign exchange buffers slightly increased as of end-October as the value of the central bank’s...

News

COVID-19 has had a significant impact on the mental health of Filipinos across different groups all over the archipelago. From frontline workers, parents balancing...

Disclaimer: Respect Investment.com, its managers, its employees, and assigns (collectively "The Company") do not make any guarantee or warranty about what is advertised above. Information provided by this website is for research purposes only and should not be considered as personalized financial advice. The Company is not affiliated with, nor does it receive compensation from, any specific security. The Company is not registered or licensed by any governing body in any jurisdiction to give investing advice or provide investment recommendation. Any investments recommended here should be taken into consideration only after consulting with your investment advisor and after reviewing the prospectus or financial statements of the company.

Copyright © 2022 Respect Investment. All Rights Reserved.